How to build your Cabin Eight Two-Tier

1

When it arrives

What comes in the crate?

The whole cabin, flat-packed in one timber crate, 3 × 1.2 × 1 m: the runners, floor, wall and roof boards and two end frames, the benches on two tiers, the glass door, the shingles, four steel straps and every fixing.

A sauna packed in its timber crate on pallets, film-wrapped and strapped
Film-wrapped and strapped, on its pallets
A sauna crate on its pallets, set down at the kerb, the lorry beyond it
Set down at the kerb, on firm, level ground
A sauna crate on its pallets at the kerb, the curtain-sided lorry stopped beside it
The lorry needs room to stop by your kerb
  • The cabin: four base runners, 101 floor, wall and roof boards, 2.95 m long, and the two end frames, every part with its code.
  • Benches on two tiers: two upper benches in an L, 205 × 55 and 214 × 55 cm, with their backrests, a lower bench 152 × 55 cm and a step.
  • The glass door: 8 mm toughened glass, 1770 × 690 mm, in its frame, with its handle and a roller catch.
  • Air, floor and drain: two vent sets for the back wall, a slatted floor section and a stainless drain plate.
  • Straps and fixings: four steel straps with their brackets, rods and nuts, and every fixing, listed by code.
  • The roof: 87 bitumen shingles, with the starter battens and the roofing nails.
  • The heater, if you added one: it travels in the same crate.
  • The cabin: four base runners, 101 floor, wall and roof boards, 2.95 m long, and the two end frames, every part with its code.
  • Benches on two tiers: two upper benches in an L, 205 × 55 and 214 × 55 cm, with their backrests, a lower bench 152 × 55 cm and a step.
  • The glass door: 8 mm toughened glass, 1770 × 690 mm, in its frame, with its handle and a roller catch.
  • Air, floor and drain: two vent sets for the back wall, a slatted floor section and a stainless drain plate.
  • Straps and fixings: four steel straps with their brackets, rods and nuts, and every fixing, listed by code.
  • The roof: 87 bitumen shingles, with the starter battens and the roofing nails.
  • The stove and flue kit: the ETNA 12 with its stand, stone guard and heat shields, and the flue kit, in the same crate.

Not in the crate

A 20 kg box of Harvia sauna stones – Cabin Eight Two-Tier sauna
Stones: 20 kg a box
  • Exterior wood treatment and a brush: a preservative or stain for the outside only, at stage 4. Any DIY shop sells it.
  • Foam and sealant: expanding foam for the ridge and the door frame, bituminous sealant and a sealant gun for the roof.
  • Sauna stones: the PC90 basket takes up to 80 kg, in 20 kg boxes, sold separately.
  • The heater circuit: your electrician’s work, not in our price.
  • Your tools: the list is on page 3 of the manual, and in the next chapter.
  • Exterior wood treatment and a brush: a preservative or stain for the outside only, at stage 4. Any DIY shop sells it.
  • Foam and sealant: expanding foam for the ridge and the door frame, bituminous sealant and a sealant gun for the roof.
  • Sauna stones: the ETNA 12 takes a full 80 kg, in 20 kg boxes, sold separately.
  • Rock wool: for round the firebox in the wall and round the flue at the roof, as the manual draws it.
  • The Part J sign-off: building control or a registered installer signs off the stove and flue: not in our price.
  • Your tools: the list is on page 3 of the manual, and in the next chapter.
1.1What arrives: in detail
Added a black-framed door or the Black Edition? The door comes in its frame, the same size; the graphite shingles go on in place of the standard ones. Chose the panoramic back wall? It is a 2100 × 1050 mm glass panel in the back wall of the hot room, fitted with the walls as appendix 2 of the manual shows. The LED lighting kit goes in with the benches, at stage 5.
2

Before you build

What do you need before you start?

Two people, the tools on page 3 of the manual, every part counted, and the base ready, level and square.

  • Two peopleTwo people build it from the manual, with ordinary tools. Rather not build it? Find a local fitter.
  • The manual, read firstOne 35-page manual for both editions, every part and step drawn: read it all before you open the crate. Skip the stove pages, 29, 31, 32 and 34.
  • Every part thereCount the parts against pages 4 to 6. Short or damaged? Note it on the delivery note, take photos and tell us within 14 days: we replace it free.
  • Within two weeksKeep the timber flat and dry until it goes in, and build within two weeks of delivery: timber that sits damp can warp.
  • The spot and the baseClose to the house, the glass door towards the fence or the house, with room to walk round it and reach the straps; the base ready, as in the next chapter.
  • Your electrician, bookedThe heater needs its own circuit from the consumer unit, 40 A for the PC90, 35 A for the BC80: a qualified electrician’s job, not in our price. Book it before delivery.

Tools · page 3 of the manual

  • Cordless drill-driver, TORX T25 and PZ2 bits
  • Drill, Ø8 mm bit
  • Jigsaw
  • Rubber mallet
  • Hammer
  • Knife
  • Two spanners
  • Tape measure
  • Spirit level
  • Sealant gun

Roof work from a stable step ladder, never from the benches.

  • Two peopleTwo people build it from the manual, with ordinary tools. Rather not build it? Find a local fitter.
  • The manual, read firstOne 35-page manual for both editions, every part and step drawn: read it all before you open the crate. The stove and flue are appendix 3, pages 29 to 34.
  • Every part thereCount the parts against pages 4 to 6 and the stove and flue set on page 8. Short or damaged? Note it on the delivery note, take photos and tell us within 14 days: we replace it free.
  • Within two weeksKeep the timber flat and dry until it goes in, and build within two weeks of delivery: timber that sits damp can warp.
  • The spot and the baseClose to the house, the glass door towards the fence or the house, room to walk round it and reach the straps, and standing room by the fire-door wall; the base ready, as in the next chapter.
  • Installer and councilBuilding control or a registered installer signs off the stove and flue under Part J: not in our price. Check smoke control at your address with your council.

Tools · page 3 of the manual

  • Cordless drill-driver, TORX T25 and PZ2 bits
  • Drill, Ø8 mm bit
  • Jigsaw
  • Rubber mallet
  • Hammer
  • Knife
  • Two spanners
  • Tape measure
  • Spirit level
  • Sealant gun

Roof work from a stable step ladder, never from the benches.

3

Before you build

What base does it need?

A firm, level base the size of the cabin, 300 × 220 cm, no larger: a concrete slab, paving slabs or compacted gravel. The cabin stands on its own four runners, 770 mm apart.

The Cabin Eight Two-Tier electric on level paving: one glass door, four steel straps, the cabin on its runners
On level paving, on its four runners
Drawing from the Cabin Eight Two-Tier manual, page 2: the plan in millimetres, 3000 × 2200 mm outside, the benches in an L
Manual, page 2 · the plan
The Cabin Eight Two-Tier wood-fired cut open along one side: the floor on its four runners, the benches in an L and the stove by the door
Cut open: the floor on its four runners
Drawing from the Cabin Eight Two-Tier manual, page 2: the plan in millimetres, 3000 × 2200 mm outside, the benches in an L
Manual, page 2 · the plan

How it stands on the ground

  • Four runners, set levelTreated first, then set level on the base, across the width, 770 mm apart.
  • Square and levelMeasure both diagonals: when they are equal, the runners are square. Then check them with the level and the tape.
  • The size of the cabin300 × 220 cm, no larger: a base that sticks out past the walls holds rain against them.
  • Free-drainingNo mains water is needed: the floor drain empties under the cabin, so the ground beneath must drain freely.
4

Building it

How is it built, step by step?

In the manual’s order: the runners and the floor, the walls and the roof curve, the drain plate, the outside treated and the vents, the benches; then the ridge and the steel straps, the door, and the shingles last.

One manual covers both editions. Skip the stove pages of appendix 3, 29, 31, 32 and 34, leave the wall opening and the flue hole uncut, and where a drawing shows a flue, leave it out.
1

Before you start · manual pages 4 to 8

Unpack and sort the parts

Photographing the crate at the kerb before signing the delivery note
Timber parts laid out on a paved path and counted
Drawing from the Cabin Eight Two-Tier manual, page 4: the runners L1950, the end frames C41 to C44, the floor, wall and roof boards, the trims and the door DG1800
Manual, page 4
Drawing from the Cabin Eight Two-Tier manual, page 5: the fixings by code, the steel straps and their fittings, the handle SET2, the vents SET3, the drain plate Q1 and the shingles
Manual, page 5
Drawing from the Cabin Eight Two-Tier manual, page 6: the benches, the backrests, the step HS1600, the floor section P1650, the legs R520 and the posts R1000
Manual, page 6

Lay everything out by code and count it against the parts pages: every part is drawn there with its code and how many come.

  • Before you sign: photograph the crate and note any damage on the delivery note.
  • Runners, end frames, boards, trims, benches, the door and the fittings, each in their own pile.
  • Every page of the manual lists the parts and fixings it uses, by code and count.
  • Anything short or damaged? Tell us within 14 days and we replace it free, delivery included.
2

Manual pages 9 and 10

Lay the runners and the floor

The stainless drain plate set into the floor boards, over the hole in the centre board
Drawing from the Cabin Eight Two-Tier manual, page 9: four runners L1950 across the cabin, 770 mm apart
Manual, page 9
Drawing from the Cabin Eight Two-Tier manual, page 10: the centre board B31 first, then nine B32 and nine B33 either side
Manual, page 10

Four runners, treated, level and 770 mm apart; then the floor, out from the centre board with its drain hole, each board screwed down and tapped home.

  • Treat the four L1950 runners and set them level on the base, 770 mm apart; check them with the level and the tape.
  • B31, the centre board with the drain hole, first; then nine B32 and nine B33 either side, 4570 screws into the runners and 45120 board to board, tapped home with the rubber mallet.
  • Treat the underside of the floor boards before they go down.
3

Manual pages 11 to 13

Stand the end frames, build the walls and the roof curve

The Cabin Eight Two-Tier with its walls and roof boards up, before the outside is treated
Drawing from the Cabin Eight Two-Tier manual, page 11: the floor drilled, the lower end frames C41 and C43 stood on it
Manual, page 11
Drawing from the Cabin Eight Two-Tier manual, page 12: the side walls, the upper frames C42 and C44, then the boards over the roof curve to a 20 to 30 mm gap at the ridge
Manual, page 12
Drawing from the Cabin Eight Two-Tier manual, page 13: the temporary battens crossed out, the drain plate Q1 over the hole in B31
Manual, page 13

The floor drilled and the lower end frames stood on it; the boards up both side walls, the upper frames on top and on over the roof curve; then the temporary battens off and the drain plate in.

  • Drill the 38 marked holes with the Ø8 mm bit, then stand the lower frames, C41 at the door end and C43 at the back, two 4570 screws each.
  • Both side walls with 14 B32 and 14 B33, then C42 on C41 and C44 on C43.
  • On over the roof curve with 25 B32 and 25 B33; cut the last boards lengthways with the jigsaw, BS32 and BS33, to leave a 20 to 30 mm gap at the ridge.
  • Take off the temporary battens and the rail across the door opening, crossed out on page 13, and fit the drain plate Q1 over the hole in B31 with four 4345 screws.
  • Chose the panoramic back wall? It goes in with the walls: appendix 2, pages 26 to 28.
4

Manual page 15

Treat the outside, fit the vents

The round timber vent valve on the inside of the hot-room wall, bare wood
The back wall of a cabin of the same range, with one vent grille high and one low
Drawing from the Cabin Eight Two-Tier manual, page 15: the outside treated from the base up to 1.6 m; the vents SET3 in the back wall, the grille outside, the valve inside
Manual, page 15

Any exterior wood preservative or stain on the outside walls, from the base up to 1.6 m; then the two vents in the back wall.

  • The outside walls from the base up to 1.6 m, where page 15 marks it; the front and back walls in full: the shingles do not cover them.
  • Outside only: the inside stays bare wood, the benches and backrests too.
  • The two vent sets SET3 in the back wall, one high and one low: the grille outside, the adjustable valve inside.
  • Pick a dry day above +10 °C.
5

Manual pages 14, 16 and 17

The benches on two tiers

Drawing from the Cabin Eight Two-Tier manual, page 14: where everything goes: the upper benches S2050 and S2140 in an L, the backrests, the lower bench S1520 and the step HS1600
Manual, page 14
Drawing from the Cabin Eight Two-Tier manual, page 16: the back upper bench S2050 on its supports and posts, the backrest H2000 above it
Manual, page 16
Drawing from the Cabin Eight Two-Tier manual, page 17: the side upper bench S2140, its backrests H1300, the lower bench S1520 and the step HS1600
Manual, page 17

Page 14 shows where everything goes; then the back upper bench with its backrest, the side upper bench to make the L, the lower bench and the step.

  • Page 14 shows the layout: the upper benches S2050 along the back wall and S2140 along the side wall, in an L, the lower bench S1520 in front and the step HS1600.
  • The back upper bench S2050 on its R520 supports and two R1000 posts, the backrest H2000 above it, as page 16 dimensions them.
  • The side upper bench S2140 with its two backrests H1300, the lower bench S1520 and the step HS1600, on their R520 legs and R1000 posts.
  • The benches stay bare wood, like the rest of the inside. Added the LED lighting kit? Fit it now, while the benches go in, as its fitting guide shows.

Wood-fired: the stove goes in now, before the ridge · appendix 3

  • Guard, stand and plateThe stone guard G4 put together round the stove G1, page 29; the stand from two B300 and two W400 with four 4570 screws, the plate G5 on it and the stove on the plate, page 30.
  • Through the side wallA 400 × 700 mm opening, 140 mm above the floor and at least 120 mm from the front wall, rock wool round the firebox, page 32; a heat shield Q3 on each wall inside, page 33.
  • The flueA 285 × 285 mm hole in the roof, 150 mm from the wall, the plate Q2 with eight 4216 screws and rock wool round the pipe, page 31; then G12 on the stove, the next section and the twin-wall G7 through the roof, page 34.
6

Manual pages 18 and 19

Close the ridge, fit the steel straps

A steel strap tensioner on the side wall: two brackets, a threaded rod and its nuts
Drawing from the Cabin Eight Two-Tier manual, page 18: the ridge gap foamed and trimmed, the battens W1350 and the blocks W80 over it inside
Manual, page 18
Drawing from the Cabin Eight Two-Tier manual, page 19: the four steel straps L60, the ends of each joined with brackets K60, a threaded rod and nuts
Manual, page 19

Foam along the ridge gap, trimmed flush, and the battens over it inside; then four steel straps round the cabin, tightened evenly.

  • Fill the ridge gap with expanding foam and trim it flush with the knife once it has set.
  • Inside, the two W1350 along the ridge, six 4345 screws each, and the four W80 blocks, two each.
  • The four L60 straps round the cabin, the ends of each joined with two K60 brackets, a 732012 rod and 2012 nuts: tighten them evenly with two spanners.
Wood-fired: as you close the ridge, pack rock wool round the flue where it passes through the roof, as page 31 shows.
7

Manual pages 20 and 21

Fit the door

The door frame and the glass door, the roller catch plate set into the frame
Drawing from the Cabin Eight Two-Tier manual, page 20: the door frame DG1800 screwed into the opening, eight screws under their caps, the gap foamed
Manual, page 20
Drawing from the Cabin Eight Two-Tier manual, page 21: the trims W1800 and W840 outside, 20 mm back from the frame
Manual, page 21

The glass door comes in its frame: screw the frame into the opening, foam the gap round it, then fix the trims outside, 20 mm back from the frame.

  • The door frame DG1800 in the opening, eight 4570 screws through it, the caps J over the heads.
  • Expanding foam in the gap round the frame.
  • Outside, two W1800 and the W840 head, 20 mm back from the frame, with 4345 screws.
8

Manual pages 22 and 23

Trims inside, the handle and the catch

The roller catch in the timber door frame, close up
Drawing from the Cabin Eight Two-Tier manual, page 22: the trims W1800 and W840 round the frame, inside view
Manual, page 22
Drawing from the Cabin Eight Two-Tier manual, page 23: the handle SET2 through the glass, and how tightly the catch holds, set with a screwdriver
Manual, page 23

The trims round the frame inside, the handle SET2 through the glass, and the roller catch in the frame, set to hold the door snugly.

  • Inside, two W1800 and the W840 head round the frame: six 4345 screws in each W1800, four in the W840.
  • The handle SET2 through the glass, as page 23 draws it.
  • The roller catch sits in the door frame: page 23 shows how to set how tightly it holds, with a screwdriver.
9

Appendix 1 · manual pages 24 and 25

Shingles, then seal the roof

Drawing from the Cabin Eight Two-Tier manual, page 24: the starter battens WS at 1.45 m, the first row of shingles nailed on them, then each next row
Manual, page 24
Drawing from the Cabin Eight Two-Tier manual, page 25: the start row and eleven more on each side, the last row over the ridge, the joints sealed along the dashed lines
Manual, page 25
Drawing from the Cabin Eight Two-Tier manual, page 1: the finished cabin from the cover: the glass door, four steel straps, the shingle roof and, on the wood-fired edition, the flue
Manual, cover · the finished cabin

The starter battens along each side at 1.45 m, the shingles in overlapping rows up to the ridge, then sealant along the joints. Then walk round once.

  • The starter battens WS along each side at 1.45 m, with 4345 screws.
  • The first row of shingles E nailed on them with 9325 nails, then each next row overlapping the one below: the start row and eleven more on each side, and the last row over the ridge, 87 shingles in all.
  • Bituminous sealant along the joints page 25 marks with dashed lines.
  • Last walk round: the straps tightened evenly, the door closing onto its catch, both vents turning freely, the outside treated and dry.
Wood-fired: the flashing G8 goes over the flue, metal side down, with twelve 9325 nails, then the rain cap G9, the joints sealed: pages 34 and 25, drawn in the stove chapter below.
5

Building it

How does the heater go in?

Once the cabin is built: the manual draws the heater on the right, in the corner by the door. A qualified electrician runs its own circuit, makes the connection and certifies the work: that is not in our price.

Sauna stones going into the basket of a Harvia Cilindro pillar heater
Stones in the basket: up to 80 kg
  • Harvia Cilindro PC90: 9 kW, with its timer and thermostat on the heater; chosen in your build. Harvia rates it for rooms of 8 to 14 m³, and this hot room is about 12 m³.
  • Harvia Vega BC80: 8 kW, wall-mounted, in place of the pillar heater, on a 35 A circuit.
  • Where it goes: on the right, in the corner by the door, as appendix 3 of the manual draws it. Harvia’s own manual, in the heater box, gives the clearances and how it is fixed: follow it.
  • The supply: its own circuit from the consumer unit, 40 A for the PC90 or 3 × 16 A three-phase, in rubber cable of type H07RN-F or equivalent, as Harvia specifies. PVC is not permitted.
  • Your electrician: fits the supply, makes the connection and certifies the work.
  • Stones: the PC90 basket takes up to 80 kg, the BC80 20 kg; sold separately and loaded as Harvia’s manual sets out.
5

Building it

How do the stove and flue go in?

During the build, after the benches and before the ridge: appendix 3 of the manual, pages 29 to 34. The ETNA 12 stands in its stone guard in the hot-room corner by the door and is fed from outside, through the side wall; the flue goes up through the roof.

A hot room laid out like the Cabin Eight Two-Tier: the wood stove in its stone guard in the corner, heat shields on both walls, the flue rising from it
A hot room laid out the same way: the stove in its corner
  • The ETNA 12: in the price, with its stand, stone guard and heat shields, in the same crate as the cabin.
  • Fed from outside: through a 400 × 700 mm opening in the side wall, 140 mm above the floor and at least 120 mm from the front wall. Leave standing room by that wall and keep the logs dry nearby.
  • The flue kit: the pipe on the stove, a transition and the twin-wall section through the roof, the roof plate, the flashing and a rain cap; a 285 × 285 mm hole in the roof, 150 mm from the wall.
  • The sign-off: building control or a registered installer, under Part J in England and Wales: not in our price.
  • Stones: a full 80 kg, sold separately.
The Cabin Eight Two-Tier wood-fired in 3D with the roof off: the benches in an L and the stove in its guard by the door
Roof off: the stove by the door
The ETNA 12 wood-burning sauna stove in its stone guard, its fire door on a tunnel through the wall
The ETNA 12: fed from outside, no glass
Split logs stacked dry under the roof of a timber log store in a garden
Keep the logs dry, under cover, nearby

The stove pages of the manual, in order

Drawing from the Cabin Eight Two-Tier manual, page 8: the stove G1, the stone guard G4, the plate G5, the flue parts G12, G6 and G7, the roof plate Q2, the flashing G8, the rain cap G9 and the heat shields
Page 8 · the stove and flue set
Drawing from the Cabin Eight Two-Tier manual, page 29: the stone guard put together round the stove
Page 29 · the stone guard
Drawing from the Cabin Eight Two-Tier manual, page 30: the stand from two B300 and two W400, the plate G5 on it, the stove on the plate
Page 30 · the stand and the plate
Drawing from the Cabin Eight Two-Tier manual, page 31: the 285 × 285 mm hole in the roof, 150 mm from the wall for a stove fed from outside, 200 mm for one fed from inside, the plate Q2 and rock wool round the pipe
Page 31 · the flue hole
Drawing from the Cabin Eight Two-Tier manual, page 32: the 400 × 700 mm opening, 140 mm above the floor and more than 120 mm from the front wall, rock wool round the firebox
Page 32 · the side-wall opening
Drawing from the Cabin Eight Two-Tier manual, page 33: a heat shield on each wall inside, behind the stove
Page 33 · the heat shields
Drawing from the Cabin Eight Two-Tier manual, page 34: G12 on the stove, then the next section and G7 through the roof; the flashing G8 with twelve 9325 nails, metal side down
Page 34 · the flue and the flashing

Stoves you can choose

StoveFed fromGlass fire doorStones, sold separately
ETNA 12 (standard)Outside, through the wallNoA full 80 kg
ETNA 12 SNInside the hot roomYes, facing the roomA full 80 kg
Stoveman 13R-LSOutside, through the wallYes, on the outside90 to 110 kg
Cozy 12 O-TWOutside, through the wallYes, on the outside90 to 100 kg
Cozy 12 with a glass doorInside the hot roomYes, facing the room90 to 110 kg
5.1Stove: in detail

If you chose the ETNA 12 SN, fed from inside, page 31 gives its flue hole, 200 mm from the wall, and no wall opening is cut. For the Stoveman 13R-LS or a Cozy 12, follow that stove’s own manual. The stove maker’s manual gives the distances to timber and how to protect the floor.

6

Building it

Where is the full manual?

In one 35-page manual for both editions: every part with its code on pages 4 to 8, the build drawn on pages 9 to 25, the panoramic back wall in appendix 2 and the stove in appendix 3.