How to build your Cabin Six Two-Tier

1

When it arrives

What comes in the crate?

The whole cabin, flat-packed in one timber crate, 3.4 × 1.2 × 1 m: the runners, floor, wall and roof boards and three frames, the benches for all three spaces, two glass doors, the shingles, four steel straps and every fixing.

A sauna packed in its timber crate on pallets, film-wrapped and strapped
Film-wrapped and strapped, on its pallets
A sauna crate on its pallets, set down at the kerb, the lorry beyond it
Set down at the kerb, on firm, level ground
The hot room of the Cabin Six Two-Tier through the inner door: the upper bench, the side bench and the lower tier
The benches: two tiers and a side bench
The roller catch in the frame of a glass door of the Cabin Six Two-Tier
Two glass doors, with roller catches
The round timber vent valve on the hot-room wall of the Cabin Six Two-Tier
The vent valve, for inside the back wall
  • The cabin: four base runners, 101 floor, wall and roof boards and three frames, for the door wall, the partition and the back wall, every part with its code.
  • Benches for all three spaces: two tiers and a side bench in the hot room, two storage benches in the changing room and two porch seats.
  • Two glass doors: 8 mm toughened glass, 1770 × 690 mm, in their frames, with timber knobs and roller catches.
  • Air, floor and drain: two vent sets for the back wall, three slatted floor sections and a stainless drain plate.
  • Straps and fixings: four steel straps with their brackets, rods and nuts, and every fixing, listed by code.
  • The roof: 100 bitumen shingles, with the starter battens and the roofing nails.
  • The heater, if you added one: it travels in the same crate.
  • The cabin: four base runners, 101 floor, wall and roof boards and three frames, for the door wall, the partition and the back wall, every part with its code.
  • Benches for all three spaces: two tiers and a side bench in the hot room, two storage benches in the changing room and two porch seats.
  • Two glass doors: 8 mm toughened glass, 1770 × 690 mm, in their frames, with timber knobs and roller catches.
  • Air, floor and drain: two vent sets for the back wall, three slatted floor sections and a stainless drain plate.
  • Straps and fixings: four steel straps with their brackets, rods and nuts, and every fixing, listed by code.
  • The roof: 100 bitumen shingles, with the starter battens and the roofing nails.
  • The stove and flue kit: the ETNA 12 with its stand, stone guard and heat shields, and the flue kit with its damper, in the same crate.

Not in the crate

A 20 kg box of Harvia sauna stones – Cabin Six Two-Tier sauna
Stones: 20 kg a box
  • Exterior wood treatment and a brush: a preservative or stain for the outside only, at stage 6. Any DIY shop sells it.
  • Foam and sealant: expanding foam for the ridge and the door frames, bituminous sealant and a sealant gun for the roof.
  • Sauna stones: the Cilindro basket takes up to 80 kg, stones of 5 to 10 cm, sold separately.
  • The heater circuit: your electrician’s work, not in our price.
  • Your tools: the list is on page 8 of the manual, and in the next chapter.
  • Exterior wood treatment and a brush: a preservative or stain for the outside only, at stage 6. Any DIY shop sells it.
  • Foam and sealant: expanding foam for the ridge and the door frames, bituminous sealant and a sealant gun for the roof.
  • Sauna stones: the ETNA 12 takes a full 80 kg, in 20 kg boxes, sold separately.
  • Rock wool: for round the firebox in the wall and round the flue at the roof, as the manual draws it.
  • The Part J sign-off: building control or a registered installer signs off the stove and flue: not in our price.
  • Your tools: the list is on page 9 of the manual, and in the next chapter.
1.1What arrives: in detail
Added black-framed doors or the Black Edition? The doors come in their frames, the same size; the graphite shingles go on in place of the standard ones. Chose the panoramic back wall? It is a 2100 × 1050 mm glass panel built into the back wall of the hot room: we confirm the layout with you before the factory builds it. The LED lighting kit goes in with the benches, at stages 4 and 5.
2

Before you build

What do you need before you start?

Two adults, the tools in the manual, every part counted, and the base ready, level and square.

  • Two adultsTwo adults build it together, from the manual, with ordinary tools. Rather not build it? Find a local fitter.
  • The manual, read firstRead it all before you open the crate and keep it with the cabin: 21 steps over 32 pages, every one drawn.
  • Every part thereCount the parts against pages 5 to 7, photograph anything damaged before you sign, and tell us within 14 days: we replace it free.
  • Within two weeksKeep the timber flat and dry until it goes in, and build within two weeks of delivery: timber that sits damp can warp.
  • The spot and the baseClose to the house, the glass doors towards the fence or the house, with room to walk round it and reach the straps; the base ready, as in the next chapter.
  • Your electrician, bookedThe heater needs its own circuit from the consumer unit, 35 A for the PC70, 40 A for the PC90: a qualified electrician’s job, not in our price. Book it before delivery.

Tools · page 8 of the manual

  • Cordless drill-driver, TORX T25 and PZ2 bits
  • Drill, Ø8 mm bit
  • Jigsaw
  • Rubber mallet
  • Hammer
  • Knife
  • Two spanners
  • Tape measure
  • Spirit level
  • Sealant gun

Roof work from a stable step ladder, never from the benches.

  • Two adultsTwo adults build it together, from the manual, with ordinary tools. Rather not build it? Find a local fitter.
  • The manual, read firstRead it all before you open the crate and keep it with the cabin: 26 steps over 37 pages, the stove at steps 13 to 17.
  • Every part thereCount the parts against pages 5 to 8, photograph anything damaged before you sign, and tell us within 14 days: we replace it free.
  • Within two weeksKeep the timber flat and dry until it goes in, and build within two weeks of delivery: timber that sits damp can warp.
  • The spot and the baseClose to the house, the glass doors towards the fence or the house, room to walk round it and reach the straps, and standing room by the fire-door wall; the base ready, as in the next chapter.
  • Installer and councilBuilding control or a registered installer signs off the stove and flue under Part J: not in our price. Check smoke control at your address with your council.

Tools · page 9 of the manual

  • Cordless drill-driver, TORX T25 and PZ2 bits
  • Drill, Ø8 mm bit
  • Jigsaw
  • Rubber mallet
  • Hammer
  • Knife
  • Two spanners
  • Tape measure
  • Spirit level
  • Sealant gun

Roof work from a stable step ladder, never from the benches.

3

Before you build

What base does it need?

A firm, level base the size of the cabin, 340 × 220 cm, no larger: a concrete slab, paving slabs or compacted gravel. The cabin stands on its own four runners, laid across the width.

The Cabin Six Two-Tier electric side on, on paving slabs: the long wall with its four steel straps, on timber runners
On its four runners, on paving slabs
The Cabin Six Two-Tier electric from the back corner, level on its runners on paving slabs
From the back corner, level on its runners
Drawing from the Cabin Six Two-Tier manual: the plan in millimetres, 3400 × 2200 mm outside, with the hot room, the changing room and the porch
Manual, page 4 · the plan
The Cabin Six Two-Tier wood-fired side on, on its runners: the fire door between the second and third straps, the flue on the roof
On its runners, the fire door in the long wall
The Cabin Six Two-Tier wood-fired cut open along one side: the floor on its runners, the benches and the stove by the partition
Cut open: the floor on its runners
Drawing from the Cabin Six Two-Tier manual: the plan in millimetres, 3400 × 2200 mm outside, the stove in the hot room by the partition
Manual, page 4 · the plan

How it stands on the ground

  • Four runners, set levelTreated first, then set level on the base, across the width, 800, 860 and 860 mm apart.
  • Square and levelMeasure both diagonals: when they are equal, the runners are square. Then check them with the level and the tape.
  • The size of the cabin340 × 220 cm, no larger: a base that sticks out past the walls holds rain against them.
  • Free-drainingNo mains water is needed: the floor drain empties under the cabin. On a slab or paving, leave a gravel-filled gap beneath it.
4

Building it

How is it built, step by step?

In the manual’s order: the runners, the floor and the frames, the walls and the roof curve, the porch seats and the benches, the outside treated; then the straps and the ridge, the doors and the vents, and the shingles last.

Some drawings are shared with the wood-fired edition and show a stove, a wall opening or a flue. Your cabin has none of these: leave those parts out.
1

Before step 1 · the parts pages

Unpack and sort the parts

Photographing the crate at the kerb before signing the delivery note
Timber parts laid out on a paved path and counted
Drawing from the Cabin Six Two-Tier manual: page 5, the timber parts: the runners, the three frames, the wall and roof boards, the trims and the two doors
Manual, page 5
Drawing from the Cabin Six Two-Tier manual: page 6, the fixings by code, the steel straps and their fittings, the knobs, the vents, the drain plate and the shingles
Manual, page 6
Drawing from the Cabin Six Two-Tier manual: page 7, the benches, the backrests, the posts and supports, the floor sections, the storage-bench lids and the porch seats
Manual, page 7

Lay everything out by code and count it against the parts pages: every part is drawn there with its code and how many come.

  • Before you sign: photograph the crate and note any damage on the delivery note.
  • Frames, boards, trims, benches, doors and fittings, each in their own pile.
  • Each step of the manual lists the parts and fixings it uses, by code and count.
  • Anything short or damaged? Tell us within 14 days and we replace it free, delivery included.
2

Steps 1 to 3 · base and floor

Lay the runners and the floor, stand the lower frames

Drawing from the Cabin Six Two-Tier manual: step 1, four runners S2000 across the cabin, 800, 860 and 860 mm apart
Step 1
Drawing from the Cabin Six Two-Tier manual: step 2, the centre board BL31 first, then nine BL32 and nine BL33 either side
Step 2
Drawing from the Cabin Six Two-Tier manual: step 3, the floor drilled, the two C41 and C43 stood on it
Step 3

Four treated runners, level, across the cabin; the floor out from the centre board with its drain hole; then the floor drilled and the lower frames stood on it.

  • Treat the four S2000 runners and set them across the cabin, 800, 860 and 860 mm apart; check them with the level and the tape.
  • BL31, the centre board with the drain hole, first; then nine BL32 and nine BL33 either side, 4570 screws into the runners, 45120 board to board, tapped home with the rubber mallet.
  • Drill the 57 marked holes with the Ø8 mm bit, then stand the lower frames: two C41, for the door wall and the partition, and C43 for the back wall, two 4570 screws each.
3

Steps 4 and 5 · walls

Build up the walls and over the roof

The Cabin Six Two-Tier with its walls and roof boards up, the porch recessed at the front, before the outside is treated
Drawing from the Cabin Six Two-Tier manual: step 4, both side walls built up, the upper frames C42 and C44 on top
Step 4
Drawing from the Cabin Six Two-Tier manual: step 5, the boards over the roof curve, the last ones cut to a 20 to 30 mm gap at the ridge
Step 5

Both side walls board by board and the upper frames on top; then the boards on over the roof curve, the last ones cut to leave a gap at the ridge.

  • Both side walls with 14 BL32 and 14 BL33, then two C42 on the C41s and C44 on C43.
  • On over the roof curve with 25 BL32 and 25 BL33.
  • Cut the last boards lengthways with the jigsaw, BS32 and BS33, to leave a 20 to 30 mm gap at the ridge.
  • Then take the temporary battens off the frames.
4

Steps 6 to 8 · inside

Porch seats and the upper bench

The porch of the Cabin Six Two-Tier: a timber seat either side of the glass door
The upper bench and its backrest along the back wall of the Cabin Six Two-Tier hot room, the lower tier in front
Drawing from the Cabin Six Two-Tier manual: step 6, where every bench, backrest and floor section goes
Step 6
Drawing from the Cabin Six Two-Tier manual: step 7, the porch seats CHL and CHR either side of the outer door
Step 7
Drawing from the Cabin Six Two-Tier manual: step 8, the upper bench S550 on its supports and posts, the backrest H2000 above it
Step 8

Step 6 shows where everything goes; then a seat either side of the porch, and the upper bench along the back wall with its backrest.

  • Step 6 shows the whole layout: the upper bench and backrest along the back wall, the lower tier in front, the side bench to the partition, a storage bench either side of the changing room and a seat either side of the porch.
  • The porch seats CHL and CHR either side of the outer door, each on an R520 leg and an R520 wall support.
  • The upper bench S550 on its wall supports and the two R1000 posts, then the backrest H2000.
  • Added the LED lighting kit? Fit it now, while the benches go in, as its fitting guide shows.
5

Steps 9 to 11 · inside

The lower tier, the side bench and the storage benches

The two tiers with their backrests and the side bench in the Cabin Six Two-Tier hot room
A storage bench in the changing room of the Cabin Six Two-Tier
Drawing from the Cabin Six Two-Tier manual: step 9, the lower tier S360 on its legs, the backrest slats W2050 on the posts
Step 9
Drawing from the Cabin Six Two-Tier manual: step 10, the side bench S500 along the side wall to the partition
Step 10
Drawing from the Cabin Six Two-Tier manual: step 11, a storage bench: the frame, the front boards and the lid on two hinges
Step 11

The lower tier in front of the upper bench, the side bench along the side wall to the partition, and a storage bench either side of the changing room.

  • The lower tier S360 in front of the upper bench on R520 legs, and the two W2050 backrest slats to the posts.
  • The side bench S500 along the side wall, from the tiers to the partition, on its R520 legs.
  • Each storage bench: an R520 frame, five W850 front boards and the lid D850 on two hinges, with R750 supports on the wall.
6

Step 12 · outside

Treat the outside, fit the drain

The stainless drain plate set into the floor boards of the Cabin Six Two-Tier
Inside the Cabin Six Two-Tier hot room: the two tiers and the walls in bare, untreated wood
Drawing from the Cabin Six Two-Tier manual: step 12, the outside treated from the base up to 1.6 m, the drain plate Q1 over the hole in BL31
Step 12

Any exterior wood preservative or stain on the outside walls, from the base up to 1.6 m; then the drain plate over the hole in the centre floor board.

  • The outside walls from the base up to 1.6 m, where the manual marks it; the front and back walls in full: the shingles do not cover them.
  • Outside only: the inside stays bare wood, the benches and backrests too.
  • The drain plate Q1 over the hole in BL31, with four 4345 screws.
  • Pick a dry day above +10 °C.

Wood-fired: the stove goes in now · steps 13 to 17

  • The two openingsA 285 × 285 mm opening in the roof, 150 mm from the wall, the plate Q2 inside with eight 4241 screws; a 400 × 700 mm opening in the side wall, 140 mm above the floor and 120 mm from the partition.
  • Guard, stand and shieldsThe stone guard G4 round the stove G1; the 400 × 300 × 110 mm stand from two B300 and two W400; the heat shields Q3 on the two walls, the stove on its stand with the firebox through the opening; outside, rock wool round it and the shield Q4 with twelve 4241 screws.
  • The flue, in orderThe pipe G12 on the stove, the damper G13 below the ceiling, then G6 and the twin-wall section G7 through the roof.
7

Manual chapter Straps and ridge

Fit the steel straps, close the ridge

A steel strap tensioner on the side wall of the Cabin Six Two-Tier: two brackets and a threaded rod
Drawing from the Cabin Six Two-Tier manual: the four steel straps L60, the ends of each joined with brackets K60, a threaded rod and nuts
Fit the steel straps
Drawing from the Cabin Six Two-Tier manual: the ridge gap foamed and trimmed, the battens W430, W850, W1850 and the W80 blocks over it inside
Close the ridge

Four steel straps round the cabin, tightened evenly; then foam in the ridge gap, trimmed flush, and the battens over it inside.

  • The four L60 straps round the cabin, the ends of each joined on the side wall with two K60 brackets, a 732012 rod and 2012 nuts: tighten them evenly with two spanners.
  • Fill the ridge gap with expanding foam and trim it flush once it has set.
  • Inside, W430, W850, W1850 and the three W80 over it, with 4345 screws.
Wood-fired, step 19: pack rock wool round the flue as you close the ridge.
8

Manual chapter Doors and vents

Both doors, the knobs and the vents

Through both glass doors of the Cabin Six Two-Tier: the changing room, then the hot room
The turned timber knobs on both sides of a glass door of the Cabin Six Two-Tier
The back wall of the Cabin Six Two-Tier with its two vent grilles, one high and one low
Drawing from the Cabin Six Two-Tier manual: each door frame DG1800 screwed into its opening, the gap round it foamed
Fit the doors
Drawing from the Cabin Six Two-Tier manual: the trims W1800 and W840 outside, 20 mm back from the frame
Trims outside
Drawing from the Cabin Six Two-Tier manual: the stops WS1750 and W800 inside the frame
Stops inside
Drawing from the Cabin Six Two-Tier manual: the knobs SET2 through the glass, the roller catch in the door frame
Knobs and catch
Drawing from the Cabin Six Two-Tier manual: the vents SET3 in the back wall C44: the adjustable disc inside, the grille outside
Vents

Each glass door comes in its frame: screwed in and foamed, trimmed outside and inside; then the knobs through the glass and the two vents in the back wall.

  • Each door frame DG1800 with eight 4570 screws, the caps J over the heads; expanding foam in the 20 mm gap round it. The same for both doors.
  • Outside, two W1800 and one W840 round each frame, 20 mm back from it; inside, two WS1750 and one W800; all with 4345 screws. Both doors open outward, away from the hot room.
  • The knobs SET2 through each glass door. The roller catch sits in the door frame; there is no key lock.
  • The two vent sets SET3 in the back wall, one high and one low: the adjustable disc inside, the grille outside.
9

Manual chapter Shingles

Shingles, then seal the ridge and the edges

Drawing from the Cabin Six Two-Tier manual: the starter battens WS1700 at 1.4 m, the first row of shingles nailed on them, then the rows up to the ridge
Lay the shingles
Drawing from the Cabin Six Two-Tier manual: bituminous sealant along the ridge and the roof edges, marked with dashed lines
Seal the ridge and edges

Four starter battens at 1.4 m, the shingles in overlapping rows up to the ridge, and sealant along the ridge and the roof edges. Then walk round once.

  • The four WS1700 starter battens, two a side, at 1.4 m, with 4345 screws.
  • The first row of shingles E with nine 9325 nails each, then the overlapping rows up to the ridge with six each: 100 shingles in all.
  • Bituminous sealant along the ridge and the roof edges.
  • Last walk round: the straps tightened evenly, both doors closing onto their catches, both vents turning freely, the outside treated and dry.
Wood-fired, step 26: the flashing G8 over the flue with twelve 9325 nails, then the clamp Q5 and the rain cap G9; seal the flashing with bituminous sealant too. It is drawn in the stove chapter below.
5

Building it

How does the heater go in?

Once the cabin is built. Our manual does not show the heater’s place in this cabin: ask us for it before you build. A qualified electrician fits the supply, makes the connection and certifies the work: that is not in our price.

Sauna stones going into the basket of a Harvia Cilindro pillar heater
Stones in the basket: up to 80 kg
  • Harvia Cilindro PC70 or PC90: pillar heaters, 6.8 kW and 9 kW, with the timer and thermostat on the heater; chosen in your build.
  • PC70E or PC90E: the same heaters with Wi-Fi control, from a separate BleBox unit outside the hot room.
  • Harvia Vega BC80: 8 kW, wall-mounted, in place of the pillar heater, on a 35 A circuit.
  • Where it goes: ask us before you build: the manual does not show it. Harvia’s own manual, in the heater box, gives the clearances to the benches, walls and ceiling, and how it is fixed.
  • The supply: its own circuit: for the PC70 1 × 35 A single-phase or 3 × 10 A three-phase, for the PC90 1 × 40 A or 3 × 16 A, in rubber cable of type H07RN-F or equivalent, as Harvia specifies. PVC is not permitted.
  • Your electrician: fits the supply, makes the connection and certifies the work.
  • Stones: the Cilindro basket takes up to 80 kg, stones of 5 to 10 cm, the BC80 20 kg; sold separately and loaded as Harvia’s manual sets out.
5

Building it

How do the stove and flue go in?

During the build, after you treat the outside: steps 13 to 17 of the wood-fired manual. The ETNA 12 stands in its stone guard in the hot-room corner by the partition and is fed from outside, through the side wall; the flue goes up through the roof before the ridge is closed.

The stove fire door open on the outside wall of the Cabin Six Two-Tier
Fed from outside, through the side wall
The stove in its stone guard in the hot-room corner by the partition door of the Cabin Six Two-Tier
Inside: the stove in its stone guard, by the partition
The Cabin Six Two-Tier hot room: the stove guard by the two tiers of benches and the round vent valve on the wall
The stove beside the two tiers
The flue through the shingle roof of the Cabin Six Two-Tier, its flashing sealed in, above the fire door and the steel straps
The flue, its flashing sealed into the shingles
  • The ETNA 12: in the price, with its stand, stone guard and heat shields, in the same crate as the cabin.
  • Fed from outside: through a 400 × 700 mm opening in the side wall, 140 mm above the floor and 120 mm from the partition. Leave standing room by that wall and keep the logs dry nearby.
  • The flue kit: the pipe on the stove, a damper below the ceiling, a transition and the twin-wall section through the roof, the roof plate, the flashing, a clamp and a rain cap; a 285 × 285 mm opening in the roof, 150 mm from the wall.
  • The sign-off: building control or a registered installer, under Part J in England and Wales: not in our price.
  • Stones: a full 80 kg, sold separately.
The Cabin Six Two-Tier wood-fired from above, the roof cut away: the stove in its guard in the hot-room corner by the partition
From above: the stove by the partition
The ETNA 12 wood-burning sauna stove in its stone guard, its fire door on a tunnel through the wall
The ETNA 12: fed from outside, no glass
Split logs stacked dry under the roof of a timber log store in a garden
Keep the logs dry, under cover, nearby

The stove steps of the manual, in order

Drawing from the Cabin Six Two-Tier wood-fired manual, page 8: the stove, its fire door and stone guard, the flue parts, the plates and the flashing
Page 8 · the stove and flue kit
Drawing from the Cabin Six Two-Tier wood-fired manual, step 13: the 285 × 285 mm opening in the roof, 150 mm from the wall, and the plate Q2 inside
Step 13 · the flue opening
Drawing from the Cabin Six Two-Tier wood-fired manual, step 14: the 400 × 700 mm opening in the side wall and the stone guard put together round the stove
Step 14 · the firebox opening
Drawing from the Cabin Six Two-Tier wood-fired manual, step 15: the 400 × 300 × 110 mm stand from two B300 and two W400
Step 15 · the stove stand
Drawing from the Cabin Six Two-Tier wood-fired manual, step 16: the heat shields on both walls, the stove on its stand, rock wool and the outer shield outside
Step 16 · the stove set in place
Drawing from the Cabin Six Two-Tier wood-fired manual, step 17: the pipe G12 on the stove, the damper G13, then G6 and the twin-wall section G7 through the roof
Step 17 · the flue, in order
Drawing from the Cabin Six Two-Tier wood-fired manual, step 26: the flashing G8 nailed over the flue, the clamp Q5 and the rain cap G9, the joints sealed
Step 26 · flashing and rain cap

Stoves you can choose

StoveFed fromGlass fire doorStones, sold separately
ETNA 12 (standard)Outside, through the wallNoA full 80 kg
ETNA 12 SNInside the hot roomYes, facing the roomA full 80 kg
Stoveman 13R-LSOutside, through the wallYes, on the outside90 to 110 kg
Cozy 12 O-TWOutside, through the wallYes, on the outside90 to 100 kg
Cozy 12 with a glass doorInside the hot roomYes, facing the room90 to 110 kg

If you chose another stove, follow its own manual: we confirm where its firebox goes before the factory builds the cabin. The stove maker’s manual gives the distances to timber and how to protect the floor.

6

Building it

Where is the full manual?

In the manual for your edition: every part on its parts pages, the tools, then every numbered step drawn, from the runners to the roof edges.

The whole manual: 32 pagesDownload the PDF
The whole manual: 37 pagesDownload the PDF